Delivering a high‑profile, immovable‑deadline programme, such as infrastructure for a major international sporting event, requires absolute confidence in schedule quality, performance data, and risk visibility. Our team was commissioned to undertake an independent programme review, assess entitlement to an Extension of Time (EOT), and rebuild the schedule to meet client and stakeholder expectations.
Independent Review & EOT Foundations
Our remit included a full evaluation of:
- Scope definition and alignment to a Work Breakdown Structure (WBS/OBS)
- Risks and opportunities
- Baseline change management and change control practices
- Performance reporting and measurement procedures
- Estimating accuracy and cost profiles
- Resource planning
- Schedule structure, logic, and quality
These steps formed the foundation for an accurate and defensible delay analysis to support an EOT claim.
Key Findings: Schedule Confidence at Only 36%
Our investigation revealed several critical issues undermining deliverability and credibility:
🔍 1. Schedule Quality Far Below Standards
🔍 2. WBS Misalignment & Missing Breakdown Structures
🔍 3. Lack of Cost Integration & Performance Visibility
🔍 4. No Baseline Change Control or Risk Register
Schedule Rebuild & Performance Improvement
Given the high‑profile, time‑critical nature of the project, recovering schedule slippage was essential. A schedule needed to be built which was:
✔ Structurally sound
✔ Aligned with scope and WBS
✔ Realistic and benchmarked
✔ Integrated and transparent
✔ Driven by monthly window analysis
✔ Supported by performance metrics
Outcome: A Defensible EOT Case & Improved Programme Control
The result was a schedule rebuilt on assured data, improved maturity, and a strengthened contractual position essential for a project operating under intense national and stakeholder scrutiny.