Operating within a nuclear‑licensed environment demands absolute clarity, robust governance, and fully assured programme data. When a major client approached Prima Uno to independently evaluate and benchmark a contractor’s schedule submission, they needed more than a routine review, they needed confidence, transparency, and expert assurance.
At Prima Uno, we specialise in programme, project and schedule assurance. We give assurance to clients on the deliverability of their projects. This case study highlights how our independent evaluation helped the client uncover risks, strengthen their programme baseline, ensure schedule quality and identify significant opportunities for performance improvement.
Our Approach: Independent, and Focused on Best Practice
Prima Uno undertook a full independent evaluation of the contractor’s submission, benchmarking it against OGC best practice and established industry standards.
Our work included:
- Forensic schedule interrogation
- Schedule quality assessment
- Cost estimate evaluation
- Validation of realistic durations
- Quantitative Risk Analysis
- Maturity assessments based on best practise methods
- Work Breakdown Structure (WBS) and scope definition review
- Interdependency and milestone verification
- Resource profiling and supply chain acquisition strategy review
This end‑to‑end review provided the client with a holistic understanding of programme performance, alignment with governance, and areas requiring corrective action.
What We Found: Gaps Limiting Schedule Confidence
Our analysis surfaced several critical issues impacting performance, risk exposure, and overall schedule confidence.
🔍 1. Lack of Visibility of Assumptions and Exclusions
Key programme assumptions were unclear or undocumented, making decision‑making highly vulnerable.
🔍 2. Excessive Resource Over‑Allocation
Resources were overstretched, with no defined organisational structure or clear roles and responsibilities, making delivery unrealistic.
🔍 3. Scheduling Tools and Processes Not Fit for Purpose
- Scheduling tools did not meet client needs.
- Master and team schedules existed but lacked integration.
- No systematic method for capturing customer requirements.
🔍 4. Weaknesses in Estimating and Cost Assurance
Although estimates existed, formal estimating techniques had not been applied. Assumptions were incomplete or undocumented.
🔍 5. Poor Scope Definition and WBS Alignment
Deliverables were poorly defined and not consistently aligned to the WBS or project objectives.
🔍 6. Milestones Without a Clear Rationale
Some milestones were identified, but the logic, justification, and sequencing were not clearly evidenced.
🔍 7. No Cost–Schedule Integration
This created significant challenges for tracking performance, understanding variance, and controlling delivery.
🔍 8. Limited Consideration of Risks and Opportunities
Risks were present, but no mitigation strategies were documented within the programme.
🔍 9. Inefficient Progress Collection
Progress updates were monthly, but only one person could access the schedule at a time, slowing reporting and reducing accuracy.
🔍 10. Lack of Change Control and Governance Discipline
Schedules were changed without baseline change control and established change control process or management oversight, creating instability and loss of confidence.
🔍 11. Insufficient Stakeholder & Management Engagement
Planning engineers lacked defined roles, and management buy‑in to the planning process was limited. Stakeholders were not formally identified or engaged.
Our Recommendations and the Path to Improvement
Prima Uno worked closely with the client to develop a roadmap for improvement, including:
✔ Clarifying and documenting assumptions, exclusions, and scope
✔ Establishing a governance‑aligned WBS and linking to the OBS which enables delivery
✔ Defining roles and responsibilities across the team
✔ Implementing consistent estimating processes
✔ Integrating cost and schedule data
✔ Introducing robust change control procedures
✔ Improving risk and opportunity management
✔ Moving to fit‑for‑purpose scheduling tools
✔ Enhancing progress collection and programme reporting
✔ Improving resource planning and removing over‑allocations
These actions collectively increased programme transparency, improved schedule confidence, and strengthened compliance with nuclear‑sector programme assurance expectations.
Prima Uno’s independent, expert-led review gave the client exactly what they needed: clarity, confidence, and control in a high‑hazard, high‑governance environment.