Winning major framework opportunities requires more than a compelling technical solution it demands robust project controls, accurate estimating, risk‑informed planning, and a fully assured tender programme. Our team was engaged to support a Tier 2 manufacturer bidding to design and produce up to 747 Self‑Shielded Boxes (SSBs) over a ten‑year period for a nuclear client.
This blog highlights how our multidisciplinary project controls team strengthened the bid, improved delivery confidence, and established a framework for long‑term manufacturing success.
The Scope: High‑Volume, High‑Spec Nuclear Manufacturing
The client sought tenderers with the capability and capacity to design and manufacture Self‑Shielded Boxes for nuclear waste movements and storage.
Key requirements included:
- An initial batch of 247 SSBs, followed by the potential manufacture of up to 500 additional units subject to future safety case approvals.
- A demand profile peaking at two boxes per week.
- Delivery of the first SSB within fifteen months of contract commencement.
- Demonstration of long‑term capacity, consistency, and cost efficiency over the full contract duration.
This required a bid built upon credible schedules, assured estimates, and a clear understanding of risk, cost drivers, and capability.
Our Team: Fully Integrated Project Controls Expertise
We assembled a multidisciplinary project controls team including:
- Senior Project Controls Manager
- Estimator
- Cost Engineer
- Lead Planner
- Junior Planner
- Part‑time Risk Manager
This combined capability ensured seamless coverage across cost, schedule, estimating, risk management, and tender governance.
Our Deliverables: Building a Robust, Defensible and Competitive Tender
1. Basis of Estimate (BOE) Development
This created a transparent and auditable estimate for the design and manufacture of all SSB units.
2. Fully Costed & Resourced Tender Programme
The schedule was cost‑loaded, resource‑profiled, and aligned to the client’s required demand profile.
3. Risk Management & Workshops
Our risk team:
- Delivered risk awareness sessions
- Facilitated risk identification workshops
- Created the project risk register
- Completed quantitative risk modelling
- Provided advice to the project team on where to place Time risk allowance and contingency risk values
This ensured the bid reflected realistic risk‑adjusted timelines and cost ranges.
4. Training Plan for the Supply Chain
We developed a training plan to support supply chain compliance with nuclear standards
5. Monthly Reporting Dashboards
Outcome: A Competitive, Assured and Credible Tender
By integrating cost, schedule, risk and performance controls into one cohesive tender strategy, we helped position the manufacturer as a capable and confident delivery partner ready to meet demanding nuclear manufacturing requirements and long‑term throughput expectations.
The sections of the tender questions that were written or supported by Prima Uno resulted in five out of five technical score. All project controls and risk related questions written, answered and the evidence given scored five out of five exceptional. Prima Uno scores very highly in tenders and supports many Tier 2, 3 and 4 companies targeting various sector tenders.